Construction Completing Early 2025
Close

By clicking submit I agree to the privacy policy

For sales enquiries

31st July 2024

Construction Update, July 2024

Back to articles

Topping Out Achieved!

In the last update, both the third and fourth-floor slab had been completed and pouring had begun on level 5 slab.

Since then, the building team have achieved topping out, marking a major milestone in the construction timeline.

Current works include internal walls and ceilings on Level 1, wall pouring on the rooftop, and wall framing in progress on Levels 2-4.

Upcoming tasks include painters scheduled to start within the next 1-2 weeks, and cabinet installers expected onsite in approximately 3 weeks.

Be sure to stay tuned for more construction updates coming soon from the SKS team.

Modele Construction Update July 2024
Modele Construction Update July 2024
Modele Construction Update July 2024
Modele Construction Update July 2024
ENQUIRE